Item
|
Due
|
Status date
|
Status
|
Progress report 2002
|
2002-08-31
|
2002-08-26
2002-12-12
|
Submitted
Accepted
|
Public web site
|
2002-09-30
|
2002-09-23
|
Available
|
Design phase complete
|
2002-11-30
|
2003-07-04
|
Done
|
Model modifications complete
|
2002-12-31
|
2002-10-23
|
Done
|
Milestone 1: Model spin-up complete
|
2003-02-28
|
2003-08-26
|
Done
|
Milestone 2: Suite of ensemble simulations complete
|
2003-05-31
|
2004-06-10
|
Coarse resolution (9 km) suite complete (8 members), fine
resolution (4.5 km) suite complete (8 members). The
delay was due to insufficient allocation of computer resources prior
to the late fall of 2003, and software problems at the HPC facility
in March through June 2004.
|
Progress report 2003
|
2003-08-31
|
2003-09-01
2003-12-15
|
Submitted
Accepted
|
Analysis of "integrated determinism" complete
|
2003-10-31
|
2004-07-01
|
Completed
|
Milestone 3: Report published
|
2003-12-31
|
2004-09-01
|
Published
|
Analysis of "three-dimensional determinism" complete
|
2004-04-30
|
2004-09-30
|
Completed
|
Milestone 4: Manuscript submitted for publication
|
2004-06-30
|
2004-09-30
|
Submitted
|
Project fact sheet
|
2004-06-30
|
2004-10-04
|
Submitted
|
Project end report
|
2004-06-30
|
2004-06-21
2004-09-20
|
Submitted
Accepted
|