Progress


Item Due Status date Status
Progress report 2002 2002-08-31 2002-08-26
2002-12-12
Submitted
Accepted
Public web site 2002-09-30 2002-09-23 Available
Design phase complete 2002-11-30 2003-07-04 Done
Model modifications complete 2002-12-31 2002-10-23 Done
Milestone 1: Model spin-up complete 2003-02-28 2003-08-26 Done
Milestone 2: Suite of ensemble simulations complete 2003-05-31 2004-06-10 Coarse resolution (9 km) suite complete (8 members), fine resolution (4.5 km) suite complete (8 members). The delay was due to insufficient allocation of computer resources prior to the late fall of 2003, and software problems at the HPC facility in March through June 2004.
Progress report 2003 2003-08-31 2003-09-01
2003-12-15
Submitted
Accepted
Analysis of "integrated determinism" complete 2003-10-31 2004-07-01 Completed
Milestone 3: Report published 2003-12-31 2004-09-01 Published
Analysis of "three-dimensional determinism" complete 2004-04-30 2004-09-30 Completed
Milestone 4: Manuscript submitted for publication 2004-06-30 2004-09-30 Submitted
Project fact sheet 2004-06-30 2004-10-04 Submitted
Project end report 2004-06-30 2004-06-21
2004-09-20
Submitted
Accepted